Brigade Calista Tower E: Milestone Release On commencement of Painting 7th to 12th Floor - Jan 2025
Brigade Calista Tower E: Milestone Release On commencement of Painting 7th to 12th Floor - Jan 2025
Brigade Calista Tower E: Milestone Release On commencement of Painting 7th to 12th Floor - Jan 2025
Brigade Calista Tower E: Milestone Release On commencement of Painting 7th to 12th Floor - Jan 2025
Tower D: Top View, Terrace slab completed - Dec 2024
Tower D: Terrace slab completed - Dec 2024
Tower D: Terrace slab completed - Dec 2024
Tower E: Top View, Terrace Floor partial area slab shuttering work in progress - Dec 2024
Tower E: Terrace Floor partial area slab shuttering work in progress - Dec 2024
Tower E: 18th Floor slab completed - Dec 2024
Tower F: Top View, 8th Floor partial area wall reinforcement work in progress - Dec 2024
Tower F: 8th Floor partial area wall reinforcement work in progress - Dec 2024
Tower F: 7th Floor slab completed - Dec 2024
Phase 1 STP: Wall and ramp reinforcement and shuttering work in progress - Dec 2024
Clubhouse: First floor Top view - Dec 2024
Clubhouse: First floor slab shuttering work in progress - Dec 2024
Phase 2 Tower A: Ground Floor slab completed and 1st floor partial area slab reinforcement and shuttering work in progress - Dec 2024
Phase 2 Tower B: Basement wall, shuttering and concrete work in progress - Dec 2024
Phase 2 Tower C: Ground Floor partial area slab completed - Dec 2024
Phase 2 STP: External wall waterproofing and backfilling work in progress - Dec 2024
Tower D Flooring: Commencement of Flooring from Ground floor to 6th Floor - Dec 2024
Tower D Flooring: Flooring work ongoing from Ground floor to 6th Floor - Dec 2024
Tower D Painting: Commencement of Painting activities from 7th floor - Dec 2024
Tower D: Painting work ongoing from 7th Floor - Dec 2024
Tower E Flooring: Commencement of Flooring from Ground floor to 6th Floor - Dec 2024
Tower E:Flooring work ongoing from Ground floor to 6th Floor - Dec 2024
Tower E Painting: Commencement of Painting activities from Ground floor to 6th floor - Dec 2024
Tower D: Top View, 18TH Floor Partial area slab reinforcement work in progress - Nov 2024
Tower D: 18th Floor partial area Slab, shuttering work in progress - Nov 2024
Tower D: 17th Floor Slab completed - Nov 2024
Tower E: Top View, 17th Floor partial area slab reinforcement work in progress - Nov 2024
Tower E: 17th Floor partial area slab reinforcement work in progress - Nov 2024
Tower E: 16th Floor slab completed - Nov 2024
Tower F: Top View, 6th Floor partial area slab reinforcement work in progress - Nov 2024
Tower F: 6th Floor partial area slab reinforcement work in progress - Nov 2024
Tower F: 5th Floor slab completed - Nov 2024
Phase 1 - STP: Wall reinforcement and shuttering work in progress - Nov 2024
Club House: Ground floor Top view - Nov 2024
Club House: Ground floor column, shuttering and concrete work in progress - Nov 2024
Phase 2 - Tower A: Ground Floor slab completed and 1st floor partial area wall and slab shuttering work in progress - Nov 2024
Phase 2 - Tower B: Basement wall, shuttering and concrete work in progress - Nov 2024
Phase 2 - Tower C: Ground Floor partial area slab reinforcement work in progress - Nov 2024
Phase 2 - STP: External wall waterproofing and backfilling work in progress - Nov 2024
Tower D Flooring: Commencement of Flooring from Ground floor to 6th Floor - Nov 2024
Tower D Flooring: Flooring work ongoing from Ground floor to 6th Floor - Nov 2024
Tower D Painting: Commencement of Painting activities from 7th floor - Nov 2024
Tower D Painting: Painting work ongoing from 7th Floor - Nov 2024
Tower E Flooring: Commencement of Flooring from Ground floor to 6th Floor - Nov 2024
Tower E Flooring: Flooring work ongoing from Ground floor to 6th Floor - Nov 2024
Tower E Painting: Commencement of Painting activities from Ground floor to 6th floor - Nov 2024
Brigade Calista Tower F: Milestone Release On Casting of Sixth Floor slab - Nov 2024
Brigade Calista Tower F: Milestone Release On Casting of Sixth Floor slab - Nov 2024
Brigade Calista Tower F: Milestone Release On Casting of Sixth Floor slab - Nov 2024
Brigade Calista Tower F: Milestone Release On Casting of Sixth Floor slab - Nov 2024
Brigade Calista Tower F: Milestone Release On Casting of Sixth Floor slab - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower D: Milestone Release - On commencement of Painting - 7th to 12th Floor - Nov 2024
Brigade Calista Tower A: Milestone Release On Casting of Ground Floor Slab - Nov 2024
Brigade Calista Tower A: Milestone Release On Casting of Ground Floor Slab - Nov 2024
Brigade Calista Tower A: Milestone Release On Casting of Ground Floor Slab - Nov 2024
Brigade Calista Tower A: Milestone Release On Casting of Ground Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Casting of Fifteenth Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Casting of Fifteenth Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Casting of Fifteenth Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Casting of Fifteenth Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Casting of Fifteenth Floor Slab - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Flooring GF to 6th Floor - Oct 2024
Brigade Calista Tower E: Milestone Release On Commencement of Flooring GF to 6th Floor - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Flooring GF to 6th Floor - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Flooring GF to 6th Floor - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Painting – Ground to 6th Floor - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Painting – Ground to 6th Floor - Nov 2024
Brigade Calista Tower E: Milestone Release On Commencement of Painting – Ground to 6th Floor - Nov 2024
Tower D: Top View, 17th floor Partial area slab shuttering work in progress - Oct 2024
Tower D: 17th Floor partial area Slab, shuttering work in progress - Oct 2024
Tower D: 16th Floor Slab completed - Oct 2024
Tower E: Top View, 15th Floor partial area slab reinforcement work in progress - Oct 2024
Tower E: 15th Floor partial area slab reinforcement work in progress - Oct 2024
Tower E: 14th Floor slab completed - Oct 2024
Tower F: Top View, 5th Floor partial area slab reinforcement work in progress - Oct 2024
Tower F: 5th Floor partial area slab reinforcement work in progress - Oct 2024
Tower F: 4th Floor slab completed - Oct 2024
Phase 1 - STP: Waterproofing and backfilling work in progress - Oct 2024
Club House: Ground floor Top view - Oct 2024
Clubhouse: Ground floor column, shuttering and concrete work in progress - Oct 2024
Tower A - Phase 2:Ground Floor partial area slab completed and 1st floor partial area wall shuttering work in progress - Oct 2024
Tower B - Phase 2: Basement wall, shuttering and concrete work in progress - Oct 2024
Tower C - Phase 2:Ground Floor partial area slab, Shuttering work in progress - Oct 2024
STP Phase 2: External wall waterproofing and backfilling work in progress - Oct 2024
Tower D - Flooring: Commencement of Flooring from Ground floor to 6th Floor - Oct 2024
Tower D - Flooring: Flooring work ongoing from Ground floor to 6th Floor - Oct 2024
Tower D - Painting: Commencement of Painting activities from Ground floor to 6th Floor - Oct 2024
Tower D - Painting: Painting work ongoing from Ground floor to 6th Floor - Oct 2024
Tower E - Flooring: Commencement of Flooring from Ground floor to 6th Floor - Oct 2024
Tower E - Flooring: Flooring work ongoing from Ground floor to 6th Floor - Oct 2024
At Calista, you don't just get a home but also get to unfold all the layers of nature and its colours.
To know more, fill in the form and we will get back to you as soon as possible.
RERA Registartion No.
Phase 1: PRM/KA/RERA/1251/446/PR/030223/005683
Phase 2: PRM/KA/RERA/1251/446/PR/220823/006195
Artist's impressions. Images and materials shown are indicative. This final product may differ based on availability.